Waterproofing System$1,850

Demo of pan, Kerdi-Board install, and 24hr flood test.

Main Floor & Wall Tile$2,400

12x24 Porcelain with 1/16" grout lines.

Grout & Sealant$450

Epoxy-based stain resistant grout in 'Driftwood'.

Total Investment $4,700.00

Agreement Terms

1. PERFORMANCE: Work performed according to TCNA standards.

2. MILESTONE PAYMENTS: Funds securely vaulted. Released to contractor solely upon photo-proof validation by homeowner.

3. MODIFICATIONS: Change orders required for any scope adjustments. Must be signed via ProLink.

4. WARRANTY: 1-Year limited workmanship warranty begins upon final ledger clearance.

Draw Signature Below
🛡️

AUTHORIZATION ONLY: A temporary hold is placed for the project value. Funds remain in your control and do not transfer until you explicitly approve timeline milestones.

Action Required

SQUARE SECURE

Release Milestone 1

Phase 1: Waterproofing & Inspection ($1,850)

Change Order #03

Custom niche tile upgrade (+ $180.00)

Project Heartbeat

📅

Next Arrival: Tomorrow @ 8:15 AM

Today @ 1:08 PM — PROOF OF WORK

Yesterday @ 4:30 PM — MESSAGE LOG

"Flood test is holding perfectly. City inspector confirmed for tomorrow morning." — Mike

Feb 18 @ 9:15 AM — PROOF OF WORK